During which phase are feasibility studies conducted?

Prepare for the AXP Exoteric Exam. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Feasibility studies are primarily conducted during the programming phase of a project. This phase focuses on defining the project’s objectives, stakeholders' needs, and ensuring that the proposed solutions are viable and beneficial. By performing a feasibility study, project teams can identify the technical, operational, and financial aspects that will impact the overall success of the project.

During the programming phase, various tools and methodologies are applied to evaluate whether the project is achievable within the set constraints, and to explore different design alternatives. This analysis allows the project team to make informed decisions before moving forward to the design phase, reducing risks associated with project viability. Failure to conduct a thorough feasibility study at this early stage can lead to significant issues later in the project lifecycle, particularly during the design and construction phases.

In contrast, the design phase focuses on developing specific solutions and detailed plans based on decisions made during the programming phase. The construction phase is about executing these plans, while the administration phase generally deals with the management and oversight of the project, rather than feasibility assessments.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy